Print

Calendar

MARCH 2012
Sunday Monday Tuesday Wednesday Thursday Friday Saturday
1 2 3
Build Team
Design & Team Presentations

4 5 6 7 8 9 10
Build Team
Design &
Discussion
11 12 13 14 15 16 17
Meeting Cancelled

Capsule Shaped
18 19 20 21 22 23 24
Build Team
Part. Collector
Micro-Ctrler
Capsule
Launch Site
25 26 27 28 29 30 31
Part. Collector
Scrubbed


Prospective
Launch Sites Selected
Helium
Picked Up



Cell Phone Activated
Capsule Assembled

Cell Phone
Test Run
Micro-Controler Completed



APRIL 2012
Sunday Monday Tuesday Wednesday Thursday Friday Saturday
1



2
Launch Window Open

Micro-Ctrler Completed

Test Flight
3


4
Components Installed &
Capsule
Sealed

Launched and Recovered Capsule
5
6





7






8

Launch
Window
Closed

9 10 11 12 13 14